Brown UniversityDesign & Construction Standards
Department of Facilities Management01 17 91OCL
BUILDING: PROJECT NAME:
OUTAGE DATE(S):
OCL REVISION #:
SECTION 01 17 91: UTILITY & CRITICAL SYSTEM OUTAGE CHECKLIST (OCL)
PROJECTIMPACTS:Detailbelowallcampusbuildings, utilitysystemsand/orbuildingsystems that
areaffected bytheproposed outage work (i.e. buildingsand buildingsystems affectedby electricalfeederworkorrepairsto steamlines;orbuildingHVACsystems, elevatorsandlighting controlsystemsaffected bybuilding firealarmsystem work, orshutdownsofuserequipment affected bybuildingprocesschilled watersystem modifications, sprinkler or fire alarm impairments):
Building(s)/ System(s) affected: / Date/starttimeof
outage: / Date/finishtimeof outage:
PREPARATORY WORK:Detail below all the requiredpreparatorywork to becompleted prior to the actual outagework(i.e. equipment rigging, installation and connections ofportable generator, shut down/ isolation ofsteam mains, switchingofcampus distribution feeders, sprinkler valve location and numbers, fire alarm zone identification, etc.):
item # / Date(s) / Description of work item
OUTAGEWORK:Detail below thesequenceofoutage and restoration work tobeperformed
(i.e. for chilled watersystem: shut down all affected equipment,LO/TO isolation valves, drain lines, makenew system connections, flush lines, test, closevalves, restore
item # / Date(s) / Description of work item
BROWNUNIVERSITY SPECIAL REQUIREMENTS:
(submit trades support work order; check offall items as applicable; add additional
project-specificitems asrequired)
Project Service Order/Work Order #
Campus utility/building record drawings
verified forproject impacts to existingutility systems and/orbuildingsystems:
GENERAL CONDITION ITEMS:
- Ifgenerators required, what size, what loads,who provides and connects?
- WeldPower (generatorserviceprovider)to beon siteto assist with generatoroperation?
- Parkinglot closureimpacts?
- Citystreet closures?
- Citypolicedetail required?
- Brown Policedetail required?
- Equipment disposal plan required?
- WasteWaterdischargepermit required?
- Fire watch needed?
FM DIVISIONS:
- Check all HVAC, fire alarm and security alarm systems during and afteroutageis complete
- Provideoverridekeys forFM staff
- Monitor critical spaces (research, artifact storage, etc)
- FumeHoods posted (ifrequired)
- Custodial post all affected buildings “closed”
- Restrict cardaccess duringtheoutage, restoreto normal post-
- ServiceResponse outagenotification to users drafted and issued
- Post notices in buildings affected
Will scheduled outage affect any fire pumps?
BROWN PUBLIC SAFETY (DPS)
- Iffirealarm oregress lighting disconnected orunreliable, verify buildings unoccupied
- Firewatch posted forbuildings without operablefire alarms (dueto project)or any buildings with impaired fire suppression systems
- Monitorsecurityalarms
- Provide card/keyaccess fortechnicians
- Check securityduringoutage
COMPUTING & INFORMATION SYSTEMS (CIS)
- Notify CIS at planning stage of all electrical outages
Email to:
- Notify CIS of system outages
Email to:
- Monitor network systems
ENVIRONMENTAL HEALTH & SAFETY (EH&S)
- Assist with posting fume hoods
- Issue hot work permits
- Assist w/fire watch coordination & notifications to AHJ
OTHER BROWN DEPARTMENTS
EMERGENCY CONTACT INFORMATION
Contractor on-site & key staff contacts:
(authorized person for sprinkler or fire alarm) / 24 hr. service #
Main #
Name / Position / Cell #
Brown on-site & key staff contacts
(responsible person) / 24 hr. service #
Main #
Name / Position / Cell #
Brown notification list: See attached
Design Submission Draft
Engineer of Record Date
Construction Submission Draft
ContractorDate
OCL Approval
Director of Operations or Facilities EngineerDate