Projects Started, Bid, Completed April 2016
- PMS Controls Upgrade Project – 640 K. Metro Controls -Finished. Commissioning Finished. Closeout, Punch list completed. Billing and final payout underway.
- Frost: Windows/Blinds – Completed, Billing and Punch list underway State Inspection on April 5 2016
- Exterior Lighting - J. Ranke Award $900K –Mostly complete. Poles on order for Frost and
- Playground
- Frost Playground .Board Approved $91,450 Grant funded Project Equipment Ordered January– Install in April
- Alcott Playground getting $20,145 Refurbished Equipment from Frost Started Equipment moved to new location
- Herrington Boiler Re commission Complete CSD1 Inspector issuing license. Violations resolved
- Alcott Boiler. Re commissioning Complete CSD1 Inspector issuing License Violations resolved
- Replacement of Sprinkler Heads Pontiac High School Completed State Inspector -no Violations
- Frost Fire Monitoring System Board Approved 12-14-2015 Grant Funded work underway
- RFP Architect of Record. Integrated Design Systems. Board Approved , Working Facilities Needs Assessment, Pontiac High School HVAC /Controls , Phase 2 and 3 Design (See Below). Evacuation Plans,
- ITA , Kennedy and WHRC- Cardinal sprinkler inspections and repairs in process. ITA state inspector signed off. Kennedy tamper valves installed and connected to system. Fire marshal expected to be out April 2016.
- Evacuation Plans for Schools finalized Almost Completed all Schools. IDS design.
- Owner Operator bids RFP underway
- CM/ Construction Manager Bid and RFP underway
- Emergency Response Bid. Co- op County Bid 50 K Estimated
- PHS HVAC Bid near completion and should be out soon.
- Phase 2 Design to go to board approved. WHRC and Admin Building for control project. Pending Capital Budget amendment number 2 FY 16. $131,075
- Frost Parking lot and Side Walk. Bid goes to board April 11 2016. Grant Funded Award Pending 103,380 Nagle Paving.
- Ansul System PHS and other buildings underway some delays in parts.
- Fire Monitoring PMS , WHRC work Completed waiting on Inspector
- Frost Grant funding Security Cameras underway
- Food Service Equipment. Going to board April 11 2016. Food Service has excess fund balance must spend down. Phase 2 spending of $595,679.00 All Schools.
- Parking lots / Sidewalk, ADA Design and Scope all Schools- Underway Nowark and Fraus. 19,300, Design underway IFB bid to follow. Funds from Sinking fund.
- Playground Design all schools Underway. Phase 1 in first year Sinking Fund FY 17.
- ITA Move and Design. Board Approved. Summer Move, More information to follow.
- HVAC Energy Management Temp connects. Underway all Schools. Metro Controls. $20,000