Landowner’s Approval for Community Schools
School :
Information prepared by:
Current DEC Rating:
- Proposal
Name of Supplier
Length of Proposed contract
- Benefits Assessment (financial)
Forecast savings over 10 years: £
Forecast savings over duration of agreement: £
- Benefits Assessment (environmental)
Average annualised KWh generation forecast
CO2 emission reduction generated
Educational awareness
- Risk Assessment
I confirm adequate insurance cover (Contractor’s insurance cover, public liability and property damage insurance cover of £10 million) will be in place by the installation of Solar Panels
I confirm that the School has complied with the County Council’s Contract Regulations in selecting the proposed supplier
Signature ……………………………………………………………………………………….
Date……………………………………………………………………………………………….
Checklist
This checklist is a guide for considerations that the applicant Community School must make and the documents to be supplied to HCC Estates & Asset Management for Landowner’s Approval
Site Layout Plan with location for PV panels marked
Structural engineer’s report addressed to the County Council and the School confirming that the relevant roof areas can support the proposed design and that no existing roof warranties are invalidated
Roof warranty
- Is there a current warranty?
- How much life is left on Warranty (E.G. relative to life of any PV contract)
- Will the guarantor agree to PV within warranty agreement
- What method of fixing can be permitted (bolt through, free standing etc)
- We would want commitment to obtain a letter from the guarantor post completion
Roof structure assessment
- Structural assessment required of existing design tolerance to include
- Weight of PV panel
- Ballast load
- Snow load
Elevation drawing
Roof plans and number of PV per block
Elevation Sun plans, indicating shadows
Cable entry detailing - description
Contractual arrangements for the temporary removal of panels for maintenance (roof leaks & repairs) or upgrade of surface. This includes management of the financial implications of temporary removal of panels.
Cancellation arrangements
Check whether planning permission is required and that the scheme complies with building regulations.
If an export meter of above 30kWh is needed the export meter must be installed through the utility supplier. Export meters of less than 30kWh can be installed by an MCS engineer.
Ensure the School is provided with a copy of the MCS certification at the end of the installation.
Ensure the contractor provides an agreed health and safety plan with the School