Bid #B38-11-12
HEAD START REMODEL - ROULEAU
SANTA CLARA COUNTY OFFICE OF EDUCATION
ADDENDUM #2
FOR
CLASSROOM REMODEL
AT
HEAD START ROULEAU SCHOOL
SANTA CLARA COUNTY OFFICE OF EDUCATION
This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents identified as bid #B38-11-12 dated5/12/12. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject the Bidder to disqualification.
- CHANGES TO PRIOR ADDENDA: N/A
- CHANGES TO BIDDING REQUIREMENTS:
- For every Bid, hardware for Doors 100A, 107A and 125A is to be included.
- SCCOE does not require that bid respondents use a preferred bond form for bid, payment and performance bonds.
- For project dates and information please see the revised schedule attached.
- Provide three add alternates on the enclosed revised bid form for Restroom 104/105; Restroom 126; and Changing Room 117 as follows:
- Add Alternate #01: Please provide separate cost for Painting;
- Add Alternate #02: Please provide separate cost for Flooring;
- Add Alternate #03: Please provide separate cost for Fire Alarm
- CHANGES TO AGREEMENT & OTHER CONTRACT FORMS: N/A
- CHANGES TO CONDITIONS OF THE CONTRACT: N/A
- CHANGES TO SPECIFICATIONS:
- Division 22:
- 220500 – Plumbing Systems – removed 2.01: B, 2.06: G, K, L and M.
- CHANGES TO DRAWINGS: N/A
- CLARIFICATION OF SCOPE OF WORK:
- Remove all existing sinks and toilets and safe off with the exception of interior office sink. Per asbestos abatement schedule.
- Demolition of all flooring will be handled by the abatement contractor and not part of scope of work. Will be completed following removal and safe off.
- Provide 4 fire extinguishers. 1 per classroom.
- For restroom fixtures the following are needed:
- RM105: WC-1, L-2
- RM104: (2)WC-3, (2)L-1
- RM126: (2)WC-3, (2)L-1
- RM117: L-2
- PRE-BID RFI RESPONSES
- Per page A1.7, detail 10, it is calling for hot mopping per IR 23-2. Please clarify if hot mopping is required?
- ANSWER: Yes. Mopping is required.
- Per page A.1.7, detail 11, it is calling for shaped clear cedar behind the wall. Please advise if something else can be used?
- ANSWER: Yes. Any hard wood without knots could be used.
- Please clarify if FRP is full height? Is the FRP on all 4 walls?
- ANSWER: Yes. All four walls are full height.
- What is the status of the asbestos survey?
- ANSWER: Included in this addendum.
- Are we responsible for the Fire Alarms?
- ANSWER: Please see Changing of Bidding Requirements.
- Will there be a special bid bond form that we will need to use? There is not one attached.
- ANSWER: Please see II Changes to bidding requirements.
- Page 3, project schedule, of the specs says Notice to proceed Friday 5/25/12 and Construction Complete Friday 7/22/12 – this is only 58 calendar days. Which of the above is to be applied for this project?
- ANSWER: Please see revised project schedule.
- Bid docs on SCCOE web site has a section 099100 Painting specification. Bid docs on Weston Miles share file site does not have a section 0099100 Painting specification. Which set of bid docs are we supposed to use?
- ANSWER: Section 099100 Painting is listed on Weston Miles Share file site. Go to bid documents, then to Specs.
Plumbing Clarifications:
- There are no provisions for hot water (all cold only?)
- ANSWER: See note 8 & 9 on sheet E1.1 for new hot water heaters to be installed.
- Is there natural gas?
- ANSWER: None
- No condensate?
- ANSWER: None
- No drinking fountains?
- ANSWER: None
- No hose bibs?
- ANSWER: None
- Only 2 floor drains?
- ANSWER: None
- No non-potable water
- ANSWER: None
- Assumptions: Quantities needed (1) WC, (4) WC-3, (5) L-1, (1) L-2
- ANSWER: Yes. Please see VII Clarification of Scope of Work
Should you have any additional questions regarding this addendum, or questions regarding the construction documents, please email them in RFI format to .
______
A. D. Bursch C.P.M.
Purchasing Manager
ccBid Files; Joe Beretta; Lesley Miles