ITEM 8
Title: Progress / Update Report
To: Local Access Forum Members
Date: 1 May 2013
Author: Public Rights of Way Officer – City of Newcastle upon Tyne
A PURPOSE OF REPORT
To inform the Forum members of issues and work undertaken in Newcastle upon Tyne in relation to the Public Rights of Way / Access network
B PROPOSED ACTION
Forum Members to note the contents and comment on the points raised within the report.
C RESOURCES APPRAISAL
Currently, no resource implications are required at this time.
D SUPPORTING INFORMATION
Capital Schemes 2012/13
Location / Scheme / CommentsStamfordham Road Bridleway / Surface & drainage improvements / Complete
Westerhope Golf Course / Surface & drainage improvements, additional signage & replacement footbridge & stile / Complete
Leazes Moor / Footpath resurfacing / Complete
Capital Schemes 2013/14
A number of schemes are currently being considered for inclusion in a programme of works that will be carried over the next three years (2013/16) giving greater flexibility to design and construction teams within the Council and therefore a better use of resources.
Definitive Map and Other Legal Issues
Modification Orders
Following the receipt of two applications the Council is in the process of making Modification Orders to add the following rights of way to the Definitive map;
· Four public footpaths on open space land at Burnham Avenue, Lemington
· One public footpath on Council land at Lansdowne Terrace East, Gosforth
Legal Orders
Footpath 4 Brunswick & Footpath6 Dinnington
The Order made under section 118 of the Highways Act 1980 to extinguish 2 public footpaths which received objections is in the process of being sent to the Secretary of State for confirmation.
Dedication
Public Bridleway at Havannah Nature Reserve
The process of dedicating land for use as a public bridleway linking Coach Lane, Hazlerigg with the existing public bridleway that runs through Havannah Nature Reserve has begun. It is expected that a decision will be made within the next two months.
Maintenance
Stamfordham Road
Tree pruning has been ordered to open up the sight lines for users of the Bridleway running from North Walbottle Road. This should make it easier/safer to cross the road at Stamfordham Road and continue on the bridleway in a northerly direction towards Whorlton Schoolhouse.
Pothole repairs have been ordered to a number of locations following damage caused as a result of the weather conditions earlier in the year.
E RECOMMENDATION
The Forum is asked to note the information outlined above.