PRE-CONSTRUCTION MEETING AGENDA
DATE:
PROJECT: A & E #:
LOCATION:
- Introduction of Personnel
- Communication – Refer to Flow Chart
- Applicable permits
- Contractor shall have competent Superintendent on site @ all times when work is taking place.
- Use of the Site - Contractor will be in charge of the site inside the project limits.
- Staging Area and Job Site Use
o Plans & Specs Requirements
o Site Access - Keys/Passes/Badges
o Job Signs
o Job Trailer and parking (personal and company vehicles)
o Security and temporary fencing
o Material and/or debris storage & disposal
o Deliveries & daily access
o Salvage materials
o Owner-furnished materials - Delivery & Coordination
o Hazardous materials
o Existing condition of site
§ Review with Owner & Architect/Engineer before construction
§ Correct and/or restore any damage to original conditions
o Use of Owner’s property, power, water, telephone & other facilities
§ Cost of using owner power
- Job Site Noise & Dust Control
o Respect users (students, residents, clients, inmates), no loud music or foul language
- Utility locates
- Scheduling / Coordination
o Construction Duration
o Contract dates
§ Start date
§ Completion date
o Hours of operation
§ Agency
§ Contractor
o Existing facilities – Phasing / Sequencing of work
o Scheduling of outages
o Moving occupants, materials, equipment, etc
§ Contractor to give Owner ___ days notice to move
- Design Intent / Contract Documents
o Brief explanation of design & special features by Architect/Engineer
o Specifications & Drawings
§ Additional sets
o Addenda
o Errors, inconsistencies or omissions
- Meetings & Inspections
o Site Inspections
o Progress / Coordination Meetings
o Architect & sub-consultants project visits
o Pre-installation & start-up meetings
o Field reports & meeting minutes
- Quality Control
o Contractor’s responsibility
o Owners expects good quality
o Unacceptable/rejected work
- Owner Testing & Inspections
o Testing Consultant
o Types of test
o Responsibilities & Requirements
o Who gets copies of reports?
o Contractor is responsible for retest $
o Quality assurance by owner is not substitute for quality control by contractor.
- Job Site Record Keeping
o Contract documents
o Maintaining as-built conditions
o Permit set of documents
o RFIs, CCDs, Change Orders, Daily Logs, Submittals, Shop Drawings, etc.
- State Forms
o Contractor must use
o Can get off web page, e-mail address is:
http://architecture.mt.gov/forms/standardforms.asp
- Pre-construction Submittals – Submit before or in conjunction with first pay request
o Schedule
§ If $ > 1mil then CPM, if $< 1mil then Bar Chart
§ Milestones & critical dates
§ Two / three week look ahead
o Schedule of Values
§ Breakdown by division – labor & materials at minimum
o List of Subcontractors & Suppliers
§ List of key personnel & contact information
- Submittals
o Submittal Schedule
o Long lead / special items / samples
o # of copies & who gets
o Response time
o Format
o Substitutions
- Request for Payment
o Number of copies to be submitted.
o Accompanied by updated schedule if changes.
o Lien releases
o Stored materials
§ Must be suitably stored and per manufacturer’s recommendation when applicable
§ Off-site - copy of invoice & applicable insurance.
§ On-site - copy of invoice
o Review at monthly progress meeting
- Questions & Clarifications
o RFIs
o Response time
o RFI log
- Modifications and/or Changes
o Must have prior approval from Architect/Engineer before proceeding with changes
o Steps
§ Designer RFP
§ Contractor cost proposal
§ Construction Change Directive
§ Change Order
o Mtg. to discuss CO’s & proposals
- Claims & Delays
o Process explained in contract documents
o Liquidated damages
- Construction Methods and Safety Procedures (Comply with OSHA)
o Means & Methods are the contractor’s sole prerogative
o Safety is responsibility of the contractor.
- Commissioning
- Training
o Follow outline in specifications
o Submit agenda and list of attendance
- Substantial Completion
o Contractual obligations fulfilled
o Formally notify Architect or Engineer for substantial inspection
§ Include list of incomplete items
o O&M manuals – Submit as package, not bits & pieces
o As-Built Drawings
- Warranty
o Starts at substantial completion and ends one (1) year from final acceptance
- Final Acceptance / Closeout
o Contractual obligations fulfilled including Consent of Surety and Contractor’s Affidavit
o Date Architect/Engineer signs final pay request unless otherwise approved in writing
o Formally notify Architect/Engineer for final inspection
o Punch-list needs to be signed & returned to Architect/Engineer
o List of extra materials
- Concerns of the Facility User
o Agency staff walk-thrus