Substance Misuse Commissioning
NHS South of Tyne & Wear PID
Project Initiation Documentfor-
Implementation of Community Contract within South Tyneside PCT Substance Misuse Commissioning Team
Document purpose:
To formally agree a contract of work between the Project Management Provider and the Project Sponsor.
Approval of this document marks the formal start of the project.
Revision Control:
Version / Date / Author / Owner / Status1 / 07/04/2009 / Christian Geisselmann / C Geisselmann / Draft
2
3
Approvals:
Name / Position / Role / Date / SignatureJanice Chandler / Project Sponsor / Team Manager / 7/4/09 / X
Mark Watson / Project Sponsor / Head of SM Commissioning / 7/4/09 / X
Sign off from the Project Management Provider denotes acceptance for and on behalf of PCT
Background
The new Standard NHS Contract for Acute Hospital Services was introduced through the Operating Framework in December 2007 for agreements between PCT’s, as commissioners, and NHS Trusts and NHS Foundation Trusts as providers. Its use will be extended to independent sector providers in late 2008 (pending legislation on their eligibility to participate in CNST).DH indicated in Health Reform in England: update and commissioning framework, (July 2006) that further contracts would be developed for mental health and other non-acute services. This commitment to develop a new contractual framework for a range of out-of-hospital services was been reinforced in the Commissioning Framework for Health and Well-being (March 2007).
The Contracts will be based upon many of the same principles and requirements of the standard acute contract, amended as necessary to take account of the different service and organisational contexts.
The Community and Mental Health Contracts have now been agreed and came into force with effect from 1st April 2009.
Reasons the project is needed
The Community Contract came into effect on the 1st April 2009 and it is imperative that thatas Commissioners within South Tyneside PCT Substance Misuse Commissioning Team we fully understand the contract and its possible impact and effect onour providers whom which we contract with. The contract is very long and quite complicated in places. A clear understanding and training for both Commissioners and Providers will be a must during initial rollout phase.The framework for the Contracts required the development of a standard contract applicable to:
- Mental health services (including pathways relevant to the NHS learning disability services)
- Community health services (including pathways relevant to the NHS learning disability services)
- Ambulance services(including Patient Transport Service)
Separate contract types will not be developed for different types of provider. A consistent contractual framework will ensure a fairer playing field.
Justification for the project
Gain a clear understanding of what the contract meansService Reviews & Improved service Delivery
Improved Outcomes
Greater Patient experience
Review of all existing systems
Possible new systems to be put in place
Outline business case / business plan alignment
Enables and effective clear understanding of the ContractDelivers agreed business targets
Consistent pathways
Performance measurement enablement
Developing existing services
Improved patient experience
Objectives
- PID and plan in place
- Review of community contractand other linked performance requirements
- Implications of community contract to World Class Commissioning, standing orders and contract law framework review
- Establish gaps and infrastructure needs for Commissioners to monitor and providers to be able to deliver contract
- Develop existing internal systems to gather information data and feed into PCT Boards
- Finalise reporting arrangements
- Communications and management development programme design and implement
Project Controls and Reporting
The project manager will report weekly with project updates via a summary report to the South Tyneside Team Manager and South of Tyne & Wear Head of Commissioning (Substance Misuse)Scope
The following areas are in scope:Review of the Community Contract and also an awareness of the Mental Health and Learning Disability Contract:
- Substance Misuse (Primary function of commissioning, Drugs & Alcohol)
- Dual Diagnosis awareness
- Mental Health awareness
- Offenders / Ex Offenders awareness
Exclusions
Currently no exclusionsSponsor
The sponsors for this project is:Janice Chandler & Mark Watson
Deliverables
Business caseBusiness plan
Implementation plan
Outcomes
Provision of enough detailed information to make an informed decision around project viability.Sufficient level of completion to take forward to next stage.
Success Criteria
There is a product which is a tangible business case and review documents that allow informed decision. Delivered to time and to cost.Measurement of deliverables, outcomes and quality
Approved documentation exists and decision made.Constraints
Availability of other specialist areas resourceAvailability of skills and resources.
Business Link (Internal)
IM&T, HR, Procurement, Finance, Contracts & performance, Commissioning (PCT)Business Link (External)
ProvidersEscalation Process
Escalation will be achieved via the Sponsor and ultimately SMT or other appropriate authorityRoles and Responsibilities
Name / Role / ResponsibilityJanice Chandler / Team Manager (SM Commissioning) / Sponsor
Christian Geisselmann / Project Manager (SM Commissioning) / Provider of Project Management
Dean Outterside / Manager or Performance / Sponsor representative
Mark Watson / Head of SM Commissioning / Sponsor
ConfidentialPage 110/09/2018
Risk LogLast Updated: / 7th April 2009
ID / TYPE / OWNER / DATE IDENTIFIED / DESCRIPTION / ACTION DUE / IMPACT / PROB / OVERALL STATUS / CONTINGENCY / LAST UPDATED
RL001 / Scope / Christian Geisselmann / 07/04/09 / Lack of information infrastructure at provider and commissioner level to deliver data between contracting parties / 07/05/09 / Medium / High / High / Have data improvement plan to allow for progress for improvement to be tracked during contract period. Performance criteria and measures based around achievement of milestones. / 24/11/08
RL002 / Budget / Christian Geisselmann / 07/04/09 / Unachievable timescales to complete the project / 07/05/09 / Medium / Medium / Medium / Clear programme management arrangements in place with strong performance and risk management. / 24/11/08
RL003 / Budget / Christian Geisselmann / 07/04/09 / Failure to agree contract deliverables / 07/05/09 / Medium / Medium / Medium / Maintain focus on NHS Operating Framework and Contract requirements
Avoidance of aspirations to expand remit of contract / 24/11/08
RL004 / Quality / Christian Geisselmann / 07/04/09 / Lack of guidance and support from PCT / 07/05/09 / Medium / Medium / Medium / Early discussion and clear communication / 24/11/08
1
Confidential
Assumptions
Support for a review of the community contract remains a priority as it came into force on 1st April 2009.Portfolio remains constant for three years as all contract awards are for a 3 year period.
Dependencies
Managers and support service staff being available and are provided with the relevant information.Timelines
Project Start:7th April 2009 / Project End:
7th September 2009
Key Milestones:
Task / Milestone Date / OwnerProject Overview & PID completed / 8th April 2009 / Christian Geisselmann
Reviewed Community Contract / 15th May 2009 / Christian Geisselmann
Produce Advice &Recommendations Paper / 19th June 2009 / Christian Geisselmann
Produce Draft Report / 10th July 2009 / Christian Geisselmann
Approve Draft Report / 17th July 2009 / Christian Geisselmann
Produce Final Report / 14th August 2009 / Christian Geisselmann
Agree Final Report / 7th September 2009 / Christian Geisselmann
Completion Guidance Notes:
Background
Brief outline of Current situation/working practices/history
Reason the project is needed
Please list Major/main Reasons that project is required
Outline business case / business plan alignment
How does the project Support the Business Plan. Please quote section/page of Business Plan
Justification for the project
Outline what would happen if the project is not devlivered
Objectives
Please list the aims of the proposed project.
Project controls and reporting
Specify the frequency of project team meeting and also the reporting measures e.g. RAG status
Milestone / Deliverable level / Project level (one overall traffic light)???Red / Overdue or will be during period. No plan / Red / One or more red on critical path
Amber / Under threat or has a plan to get back on track / Amber
Green / On track / Green
Scope
List what is covered by the project.
Exclusions
List what is NOT included in the project (What is out of Scope?)
Sponsor
The Sponsor owns and is ultimately responsible for the project. They are supported by the Assistant Director and the Project Managers
Deliverables
List the changes that will be implemented.
Outcomes
List the Benefits and the Measurable Outcomes (include Quality Criteria if applicable)
Success Criteria
Define how the sponsor will know that the project has been a success
Measurement of deliverables, outcomes and quality
How can the success factors be measured?
Constraints
What are the known limitations at the outset?What are the likely limitations?
Business Link (Internal)
Links to areas and resource that are local to the provider area and within the provider area control
Business Link (External)
Links to areas that are not local to the provider area and may not be assumed to be available e.g. HR, IM&T, Estates.
Risks
The risk log at the point in time this document is created
Assumptions
What assumptions exist around the project
Dependencies
What dependencies exist between other projects or deliverables?
Timelines
Show the project start and end dates
Show the key milestones, dates expected and milestone owner.
1
Confidential