DIV 2-28
January 28, 2014 / Project: / Franciscan Towers
San Francisco, CA
Bid Date: / Friday, February 28, 2014
@2pm

Dear Subcontractors:

Nibbi Brothers has been selected as the General Contractor for the Franciscan Towers project in San Francisco, CA. We are requesting proposals from subcontractors and suppliers including those certified with the San Francisco Human Right Commission as local business enterprises (LBE’s). Subcontractors received an email notification via NewForma to download associated documents in order to providebids no later than Friday, February 28,2014 @2:00pm.Please fax or email back this form within 24 hours of receipt confirming your interest in the project to (415) 241-2951.

Project Name: Franciscan Towers

Project Location: 217 Eddy Street, San Francisco, CA

Owner:TNDC

Architect: Barcelon + Jang

Project Description:

Selective demolition with rebuild/repairs (in kind) to the building due to fire and building wide upgrades. Replacement of elevator and trash chute. Replacement of existing fire sprinkler in common corridors and fire alarm system. Replacement of lobby. Units (47 total) affected by fire shall be rehabilitated with new finishes and insulation. All units shall receive paints, finishes, doors and hardware, plumbing fixtures, cabinetry, appliances, radiators, electrical, HVAC, and smoke alarm. Further provisions include up to 20 accessible units, new community room, extensive plumbing replacements, HVAC upgrades, window replacement, and exterior paint throughout the building.

Franciscan Towers is a six-story mixed-use building located at 201-229 Eddy Street at the corner of Taylor Street in San Francisco. The ground floor contains the Tenderloin Neighborhood Development Corporation (TNDC) main office and the TNDC-operated Tenderloin after School Program (TASP). The residential portion of the building, entered through 217 Eddy Street, contains 105 units of affordable housing: five one-bedroom units, 75 efficiency studios and 25 large two-room studios.

Labor Requirements:Prevailing Wage

Project Schedule:Start: April 2014 Completion: July 2015

Mandatory Pre-Bid Meeting:Monday, February 3, 2014.

Location: Nibbi Office, 180 Hubbell Street, SF, CA

*** Please see below for your allocated time per trade****

10am – 11am (DIV 2-7)

11am – 12pm (DIV 8-28)

Job Walk: Thursday, February 6, 2014.

Location:145 Taylor Street (Meet in Curran House Lobby), SF, CA

Time:8:00am (All Divisions)

Make Up Job Walk: Thursday, February 13, 2014

Location:145 Taylor Street (Meet in Curran HouseLobby), SF, CA

Time:8:00am (All Divisions)

Bid Documents:

A link has been sent via a Newforma email notification. To have the link resent, please email Kristin Medwick at . For questions regarding this project, please contact Igor Bershteyn via email, .

Bidding: Bid proposals shall be submitted no later than 2:00 PM onFriday, February 28, 2013via email to or faxed to (415) 241-2951.

Prequalification Process:

Unless otherwise directed or authorized, in writing, by Contractor, all Subcontractors shall be required to pre-qualify with Textura Corp. upon request and at Contractor's sole discretion, and in all cases prior to Contract award and at any time during the entire duration of the Contract.

Please fax or email back this form confirming your interest in this project to (415) 241-2951.

For questions regarding this project, please contact Igor Bershteyn via email,

Thank you.

PreconstructionEstimating

WILL BID AND ATTEND PRE-BID MEETING

YES / NO
Company / Contact Name
Trade / Email Address

100 % Payment and Performance bonds from a treasury rated surety in the full amount of the subcontract may be required for this project.