BEAP Site:

Inspection Date: / /

Communications Room Checklist

Preliminary Details

Building Number
Room Number
DEMS number
ROMAN number
Location / Coordinates
Photos start at No.

Security Rating Checklist

Highest classification cabling / network equipment in room / UNCLAS
RESTRICTED
SECRET
Security rating requirement / Intruder Resistant
Secure Area
Intruder Resistant Area Checklist / Secure Area Checklist
Walls extend from base of floor to underside of slab or secured roof structure? / Yes
No / Is the space wholly located within the perimeter of a building which meets Intruder Resistant requirements? (attach assessment sheet) / Yes
No
If No, is an additional barrier installed which reaches the underside of slab or secured roof structure? / Yes
No / Walls extend from base of floor to underside of slab or secured roof structure? / Yes
No
If No, is an additional barrier installed which reaches the underside of slab or secured roof structure? / Yes
No
What type of additional barrier is installed? / Stud/plasterboard
Mesh, installed to security standard
Other (specify) / What type of additional barrier is installed? / Stud / plasterboard / plywood
Mesh, installed to security standard
Other (specify)
Wall construction / Concrete
Brickwork
Stud/Plasterboard
Other (specify) / Wall construction / Concrete
Brickwork
Stud / plasterboard / plywood
Stud / plasterboard / steel plate
Other (specify)
Roof construction / Concrete
Sheet metal
Other (specify) / If the wall construction is stud/plasterboard/plywood, is the plywood on the external wall face? / Yes
No
Unable to check
Are windows or glazing installed in walls? / Yes
No / Are joins in plywood at studs / noggins only? / Yes
No
Unable to check
If yes, is the glazing secured to the frame in a tamper evident fashion? / Yes
No / Do joins in plasterboard line up with joins in plywood? / Yes
No
Unable to check
Are blinds or drapes installed over glazed areas? / Yes
No / Roof construction / Concrete
Sheet metal
Other (specify)
What level of the building is the room in? / If the roof construction is concrete, is the slab thickness >100mm with F82 wire mesh reinforcement? / Yes
No
Unable to check
Is there additional protection installed to glazing? / Yes (specify)
No / If the roof construction is sheet metal or other, is F82 welded wire mesh installed on the roof as per the security standard? / Yes
No
How many doors are there to the space? / Are windows or glazing installed in walls? / Yes
No
Are all door thicknesses >38mm? / Yes
No / If yes, is the glazing secured to the frame in a tamper evident fashion? / Yes
No
Are all doors constructed from flush panel, block timber and have a solid core? / Yes
No / Are blinds or drapes installed over glazed areas? / Yes
No
Do all doors (excluding fire exits) have a double cylinder mortice lock? / Yes
No / What level of the building is the room in?
Do all fire exit doors have either a double cylinder mortice lock or external cylinder and internal manual turn knob? / Yes
No / Is there additional protection installed to glazing? / Yes (specify)
No
Are deadbolts installed to all doors? / Yes
No / How many doors are there to the space?
Are door hinges internal to the space and have security hinge bolts and lock bolts protectors fitted? / Yes
No / Are all door thicknesses >45mm? / Yes
No
Are door closers fitted to all doors? / Yes
No / Are all doors constructed from flush panel, block timber and have a solid core? / Yes
No
If double doors are installed, is the inactive leaf secured with flushbolts or locking padbolts? / Yes
No
N/A / Do all doors (excluding fire exits) have a double cylinder mortice lock? / Yes
No
Does the locking scheme comply with egress requirements of the BCA? / Yes
No / Do all fire exit doors have either a double cylinder mortice lock or external cylinder and internal manual turn knob? / Yes
No
Are there any penetrations over 280mm diameter or 280mm side length into the space? / Yes
No / Are deadbolts installed to all doors? / Yes
No
If yes, are security grilles fitted to the applicable penetrations? / Yes
No / Are door hinges internal to the space and have security hinge bolts and lock bolts protectors fitted? / Yes
No
Are there at least 3 hinges per door? / Yes
No
Are the door frames made or cold formed steel with minimum thickness 1.6mm? / Yes
No
Are door closers fitted to all doors? / Yes
No
If double doors are installed, is the inactive leaf secured with flushbolts or locking padbolts? / Yes
No
N/A
If locking padbolts are installed, do they have SCEC endorsed locking cylinders? / Yes
No
Does the locking scheme comply with egress requirements of the BCA? / Yes
No
Are there any penetrations over 150mm diameter or 150mm side length into the space? / Yes
No
If yes, are security grilles fitted to the applicable penetrations? / Yes
No
Additional Notes

Sketch of Room

Include internal dimensions, racks, rack dimensions, frames, entrances, penetrations and any other relevant details

Room Checklist

Room internal dimensions (mm) / Length (mm):
Width (mm):
Is there at least 900mm clear space at the front and rear of all racks? / Yes
No
Internal dimensions / Length (mm):
Width (mm):
Does the room have anti-static flooring installed as per AS 2834? / Yes
No
Is there a building Entrance Facility within the room? / Yes
No
If yes, where do conduits turn up? / Within rack
Within room
Through wall
Other (specify)
How many conduits enter the room?
What % spare capacity is there within the entrance facility conduits?
Is the lead-in cabling correctly secured to a tray, basket, ladder or conduit? / Yes
No
What type of cable containment exists to/from racks? / Conduit
Basket
Tray
Ladder
Other (specify)
What % spare capacity is there in the most full cable containment?
Is all cable containment readily accessible (i.e. access to lay in trays, conduits have draw wire installed)? / Yes
No
Are cables protected from sharp edges at all times? / Yes
No
What condition is the cabling within the room in? / Good
Fair
Poor
Other / mixture (specify)
Are cable bending radii observed for all cables within the room? / Yes
No
Are appropriate separation distances maintained between power and communications cables? / Yes
No
Are appropriate separation distances maintained between cables of different security classification? / Yes
No
Are all cable sheath colours as per the ISM? / Yes
No
Is all labelling installed within the room as per the DCCS? / Yes
No
Is there 24/7 air conditioning installed to the room? / Yes
No
If yes, what is the capacity of the air conditioning unit(s), in kW?
If the air conditioning unit(s) is labelled, what is the designation of the unit?
Is there a distribution board installed within the room? / Yes
No
What is the label on the distribution board serving the room?
How many spare ways are there in the distribution board serving the room?
Does each rack have at least 2x20A captive single phase outlets? / Yes
No
Is there a Communications Earthing System link bar installed within the room? / Yes
No
Is there an individual earth cable installed from each rack to either a CES link bar or to the earth bar of the nearest distribution board? / Yes
No
If the racks are powdercoated, has the connection point of the earth cable been stripped back to bare metal? / Yes
No
What type of fire detection is installed in the room? / Smoke detectors
VESDA
None
Other (specify)
What type of fire suppression is installed in the room? / Sprinklers
Other (specify)
Are all penetrations to the room firestopped? / Yes
No
What method of firestopping is used? / Specify:
How many racks are there in the room?
What are the attached rack checklist numbers?
How many telephone frames are there in the room?
What are the attached telephone frame checklist numbers?

Additional Notes

Provide a description of any floor standing equipment not covered above, along with any additional observations.

Base Engineering Assessment Program Checklist Template

2. ICT Communications Room Inspection Checklist.docxPage 1 of 9