<Consultant Logo Here>
CHECK LIST FOR FOUNDATION
Project / DateOwner
Consultant
Contractor
Bldg. permit
Location
Structural Part / Foundation
GENERAL ITEMS / G-1 / Proper Project Signboard and Safety Signboard placed as per regulation /
G-2 / Proper Fencing with temporary Gates within allowed limit /
G-3 / No Construction Materials / Excavated soil kept outside of fencing. /
G-4 / All safety standards are following properly. /
G-5 / All project documents are available in site /
G-6 / Proper &Safe access to site with no obstructions in paths /
G-7 / Proper House Keeping & site organization /
Common Items In Foundation / F-001: Orientation of Project, Setback Grid lines with Right Angle (90 Degree) & Distance as per drawing
OK / / Remarks
F-002: Excavation Level , Approx. Datum level point
OK / / Remarks
F-003: Concrete curing requirements are provided in site ( cube and casted concrete)
OK / / Remarks
F-004: PCC below Foundation as per drawing and polythene sheet had been provided
OK / / Remarks
F-005: Orientation & Location of Columns are as per drawing
OK / / Remarks
F-006: Foundation size, Orientation & Location as per drawing , 50mm Cover Blocks provided properly
OK / / Remarks
F-007: Re-bar dia., placement; Overlap and verticality as per drawing
OK / / Remarks
F-008: Anti Termite Treatment applied Below PCC /
F-009: Level Machine are available on site
OK / / Remarks
F-010: Demarcation of site rechecked by survey department and it is available on site
OK / / Remarks
F-011: Rebar of Each Dia. & Concrete Mix-design(for building) as per drawing
OK / / Remarks
F-012: Pile Dowels length as per regulation
OK / / Remarks
F-013: Flexible separation sheet between two adjacent footing/ structure
OK / / Remarks
Other Remarks
Consultant
Signature and stamp