SUB:- Demolition/sealing action during the month of June-2015

Sl. No. / Date / Property No. / Details of Action Taken
1 / 01.06.15 / AC-180D, Shalimar Bagh / Demolished one room and partition wall and removing shuttering at top floor at ongoing stage.
2 / 1036, Rani Bagh / Demolished roof slab of one room at SF at ongoing stage.
3 / 02.06.15 / BJ-127, West Shalimar Bagh / Excess coverage at back side at third floor has been demolished.
4 / 03.06.15 / GH-13/768, Paschim Vihar / Roof and partition wall has been demolished and made unusable at ongoing stage.
5 / 04.06.15 / BG-3/66A, 66B, 66C & 66D, Paschim Vihar / Projection on govt. land has been demolished by cutting with gas cutter at ongoing stage.
6 / A-672, Saini Mohalla, Nangloi / Roof slab of second floor and walls are dmamged. File No. 72/UC/B/RZ-I/15 dated 15.05.15 (Regular action)
7 / 05.06.15 / AU-168, DDA Flat, Pitampura / Demolished partly the roof of kitchen along with partition walls. File No. 51/UC/B/RZ-I/15 dated 08.04.15 (Regular action)
8 / RU-225, Pitampura / Demolished the roof of two rooms alongwith the removal of centering & shuttering of one and made it unusable and unhabitable at ongoing stage.
9 / H. No. 104, Part (KH. No. 487), Near Ramleela Ground, Peeragarhi Village / Property has been sealed at one point at the entry gate under unauthorized construction.
10 / 15.06.15 / QU-173A, DDA Flat, Pitampura / The roof slab of front portion i.e excess coverage demolished partly. File No. 73/UC/B/RZ-I/15 dated 18.05.15 (Regular action)
11 / QU-173B, DDA flat, Pitampura / The roof slab along brick wall demolished partly. File No. 74/UC/B/RZ-I/15 dated 18.05.15 (Regular action)
12 / QU-173C, DDA flat, Pitampura / The roof slab of second floor has been demolished. File No. 75/UC/B/RZ-I/15 dated 18.05.15 (Regular action)
13 / QU-103C, DDA Flat, pitampura / The roof slab of room alongwith partition brick wall demolished. File No. 56/UC/B/RZ-I/15 dated 22.04.15 (Regular action)
14 / L-14, DSIIDC, Peeragarhi,, Udyog Nagar / Demolished the brick walls at ground floor in the shape of two rooms at ongoing stage.
15 / 16.06.15 / A-49, Multan Nagar / Room constructed at stilt floor has been demolished by heavy hammer at ongoing stage.
16 / 31, Subh Apartment, Pitampura / Erections of walls at roof of FF has been demolished completely( newly constructed) at ongoing stage.
17 / 2, Sharda Apartment, West Enclave, Pitampura / Balcony at front portion has been removed/demolished completely at FF at ongoing stage.
18 / 17.06.15 / RZE-206, Nihal Vihar / Brick walls are damaged of FF & SF.File No. 50/UC/B/RZ-I/15 dated 08.04.15 (Regular action)
19 / 247, Rishi Nagar / Ground floor roof has been partly demolished and made unusbale at ongoing stage.
20 / 18.06.17 / B-3/37, Paschim Vihar / Roof of one room and wall has been demolisehd by heavy hammer File No. 66/UC/B/RZ-I/15 dated 06.05.15 (Regular action).
21 / 18.06.15 / G&JU-38D, Pitampura / Demolished the mumty alongwith unrooted the m.s door and also brick wall. File No. 52/UC/B/RZ-I/15 dated 08.04.15 (Regular action)
22 / G&JU-32B, Pitampura / Removed the bathroom/wc completely at ongoing stage.
23 / 19.06.15 / AC-177, Shalimar Bagh / Demolition action taken by way of demolished projection and removing shuttering at ongoing stage.
24 / RZB-21B, Laxmi Park, Nangloi / Walls are damaged on SF at ongoing stage.
25 / 22.06.15 / WP-203C, Pitampura / Demolished partly the internal brick wall along with roof of room at back portion at ongoing stage.
26 / A-5B/335, Paschim Vihar / Room constructed at the roof of the property with help of hammer and gas cutter at ongoing stage.
27 / A-4/194 Janta flat, Paschim Vihar / Roof slab of SF has been demolished by heavy hammer at ongoing stage.
28 / 23.06.15 / GH-6/69, White Apartment, Paschim Vihar / Shuttering and projection has been removed at FF at ongoing stage.
29 / AG-392, Shalimar Bagh / Demolisehd projection at stilt and GF at front side projection at ongoing stage.
30 / 24.06.15 / BH-715C, Shalimar Bagh / Room/floor constructed at roof of floor constructed over BH-715C has been demolished by heavy hammer/gas cutter at ongoing stage.
31 / CC-20D, Shalimar Bagh / Room constructed at the roof of CC-20D has been demolished by gas cutter and heavy hammer at ongoing stage.
32 / WP-10B, DDA Flat, Pitampura / Demolished the remaining portion of projection over Mpl land alongwith cupboard on projction. File No. 181/UC/B/RZ-I/11 dated 19.12.11 (Regular action)
33 / 25.06.15 / C-70, Amanpuri, Nangloi / The roof of the third floor is completely damaged and wall are damaged. File No. 20/UC/B/RZ-I/15 dated 26.02.15 (Regular action)
34 / 1038, Rani Bagh / Demolished roof slab of third floor at ongoing stage.
35 / 26.06.15 / WP-11C, DDA Flat, Pitampura / Demolished/removed the remaining portion of brick wall over parapet wall alongwith M.S Iron door competely. File No. 102/UC/B/RZ-I/14 dated 11.07.14 (Regular action)
36 / WP-10B, DDA Flat, Pitampura / Removed/cut the TMT bar i.e reinforcement of projection with gas cutter. File No. 181/UC/B/RZ-I/11 dated 19.12.11 (Regular action)
37 / B-3/57, Paschim Vihar / Roof slab of third floor and partition wall has been demolished with the help of gas cutter and heavy hammer. File No. 82/UC/B/RZ-I/15 dated 09.06.15 (Regular action)
38 / 29.06.15 / CC-22D, Shalimar Bagh / Projection and roof slab of room constructed at roof has been demolished at ongoing stage.
39 / G-78, Nihal Vihar / Demolition action has been taken by cutting the platfarm between the property at ongoing stage.
40 / 30.06.15 / D-22, Pushpanjali Enclave, Pitampura / Deviation on stilt floor and ground floor has been demolished at back side at ongoing stage.