Metro Wastewater Reclamation District
Environmental Management System for Biosolids
Element 5: Goals and Objectives for April 2013 – March 2014 with Associated Strategies
Approved By:
/ Date: 10/11/13 for September 2013GOAL 1: Beneficially reuse 100 percent of the biosolids produced April 1, 2013 to March 31, 2014
Objective / ResponsiblePerson(s) / Milestones / Targeted
Completion Date / Actual
Completion Date / Required
Resources
Land apply 92 to 94 percent of biosolids produced from April 1, 2013 – March 31, 2014 to private sites and/or the METROGRO Farm. / · Director of RR&R
· RR&R Staff / · Comprehensive Monthly Operations Summary Report produced for the previous month by the 30th of each month
· Annual Biosolids Report / Monthly Report
February 19, 2014 / 05/13/13, 06/05/13, 07/09/13, 09/09/16
10/10/13 / · Staff
· RR&R Annual Budget
Maintain contract with private compost facility to process 6 to 8 percent of biosolids produced in 2013. / · Director of RR&R
· RR&R Staff / · Contract
· Comprehensive Monthly Operations Summary Report produced for the previous month by the 30th of each month
· Annual Biosolids Report / December 2014
Monthly Report
February 19, 2014 / 05/13*13, 06/05/13, 07/09/13, 09/09/13
10/10/13 / · Staff
· RR&R Annual Budget
Begin development in 2013 of a new tenant-farmer lease agreement to be implemented in 2015. / · Director of RR&R
· Deputy Manager
· General Counsel
· RR&R Staff / · Developed estimated costs for contract farm operations / September 2013 / 07/18/13 / · Staff
· RR&R Annual Budget
GOAL 2: Inform and consider input from interested parties regarding the EMS and biosolids management activities during 2013
Objective / ResponsiblePerson(s) / Milestones / Targeted
Completion Date / Actual
Completion Date / Required
Resources
Conduct a Wastewater and Renewable Resources teacher in-service training in June 2013. / · OOM Public Information Staff
· Director of RR&R
· RR&R Staff / · Conduct in-service training / June 2013 / 06/19/13 / · Staff
· RR&R Annual Budget
Objective / Responsible
Person(s) / Milestones / Targeted
Completion Date / Actual
Completion Date / Required
Resources
Hold a field day activity at the METROGRO Farm in June 2013. / · OOM Public Information Staff
· Director of RR&R
· RR&R Staff
· RR&R Project Coordinator / · Develop agenda
· Develop information stations
· Create/send invitation
· Hold field day / May 2013
June 2013
May 2013
June 2013 / 05/13
06/13
05/13
06/15/13 / · Staff
· RR&R Annual Budget
Meet with the Citizen Participation Group (CPG) at least four times during 2013. / · Director of RR&R
· RR&R Staff
· OOM Public Information Staff
· RR&R Project Coordinator / · CPG Meeting minutes / February 2013
May 2013
September 2013
November 2013 / 02/11/13
06/03/13
09/18/13 / · Staff
· RR&R Annual Budget YR 2013 - $1,800
Meet with METROGRO Farm Stakeholders once in 2013 / · Director of RR&R
· RR&R Staff
· RR&R Project Coordinator / · Meeting minutes / September 2013 / 09/18/13 / · Staff
Present “Improving Public Communication and Outreach at the METROGRO Farm” paper at the 2013 WEF Residuals and Biosolids Conference. / · Director of RR&R
· RR&R Staff
· OOM Public Information Staff / · Present paper / May 2013 / 05/13 / · Staff
Present “Long-term Monitoring Results for the METROGRO Farm Near Deer Trail, Colorado paper at the 2013 WEF Residuals and Biosolids Conference / · Director of RR&R
· RR&R Staff / · Present paper / May 2013 / 05/13 / · Staff
GOAL 3: Identify opportunities to improve biosolids quality and value of biosolids products to end-users and complying with all applicable biosolids regulations during 2013
Objective / ResponsiblePerson(s) / Milestones / Targeted
Completion Date / Actual
Completion Date / Required
Resources
Develop RR&R Operator job descriptions which include ABC’s Biosolids Land Appliers certification requirements / · Director of Admin Services
· HR Staff
· Director of RR&R
· RR&R Staff / · Develop RR&R Operator I, II and III job descriptions
· Meet with HR Staff to develop timeline for implementation / April 2013
June 2013 / March-July 2013
05/23/13 / · Staff
Develop and implement analytical methods for nutrients using solids methods to be reported in ug/g in 2013 / · Director of ES
· ES Staff / · Method development
· Analytical code updates
· Implementation / December 2013
Evaluate impact of phosphorus in Biosolids on land application by December 2013. / · Director of RR&R
· RR&R Staff
· RWHTF Director of O&M
· RWHTF O&M Staff / · Complete Revised Universal Soil Loss Equation, Version 2 (RUSLE2) and the Wind Erosion Prediction System (WEPS) model training.
· Begin Indexing application sites to verify the biosolids application rates will meet the requirements of COPI. / May 2013
June 2013 / 02/06/13 and 02/28/13
02/07/13 / · Staff
Participate in the North American Proficiency Testing program and apply for the Proficiency Assessment Program, adopted by the NRCS as part of the phosphorus indexing of land application sites / · Director of ES
· ES Staff / · Develop WEP method
· Analytical code updates
· Implementation
· Submit quarterly sampling results for annual PAP certification / December 2013
TF\OPER 40.30 METROGRO\EMS Workpapers\Element 5 – Goals & Objectives\EMS Goals and Objectives for April 2013 – March 2014 with Associated Strategies 10-11-13.doc 3 of 3