BIOLOGICAL WARFARE DETECTORS

Note: Codes can be obtained from secure access at the below listed address. Ref CENTCOM message 190753Z APR 03 SUBJ: BIOLOGICAL WARFARE AGENT DETECTION AND ANALYSIS GUIDANCE (U)

www.centcom.smil.mil/cdi/files/Msgs_of_Interest/txt/2003/20030421_Bio_Detection.text

1. Dry Filter Unit (DFU): / IAW / S/U
a. Are the required number of DFUs with accessories on board per class? / Ref (d)
1.  Inlet Stack Filter Manifold (1) / Ref (b)
2.  Filter cartridges (4)
3.  Power Cord (1)
4.  Attached inlet cover (1)
b. HHA Immuno-assay detectors will be provided by the CBR RAV Team / Ref (c,e)
c. Training HHA Immuno-assay detectors will be provided by the CBR RAV Team / Ref (d)
d. Is dedicated refrigerator onboard, designated and labeled “FOR STOWAGE OF BIO CONSUMABLES ONLY”? / Ref (e)
e. Is refrigerator electrically safety checked?
f. DFU sampling kits will be provided by the CBR RAV Team / Ref (e)
g. Are DFU Power Cords safety checked?
h. Does the DFU vacuum work if plugged in and tested?
i. Contents of BRK as follows: / Ref (c)
1.  Bag, Kit Flyers / 1 ea
2.  Shipper, SAF-T-PAK 100 / 2 ea
3.  Sample container with spoon / 5 ea
4.  Logbook / 1 ea
5.  Scissors, Bandage / 1 ea
6.  Stopwatch / 1 ea
7.  Bag, Sealable, Plastic 10” x 10” / 20 ea
8.  Bag, Sealable, Plastic 2 Gallon / 20 ea
9.  Swab, Dacron Tip, Wood shaft, Sterile / 50 ea (2 PG)
10.  Pipette, Transfer Large / 5 ea (1 PG)
11.  Tape, Transparent Roll / 1 ea
12.  HYPE Wipes (Towelette) / 10 ea (1 PG)
13.  Under pad, Absorbent / 20 ea
14.  Labels, Blank, Specimen / 50 ea
15.  Labels, Danger Aircraft / 2 ea
16.  Labels, Class 6.2 Infectious Substance / 2 ea
17.  Label, Over pack / 2 ea
18.  Dangerous Goods Declaration / 6 ea
IAW / S/U
2. JOINT BIOLOGICAL POINT DETECTION SYSTEM (JBPDS) / 6641/054
a. External Intake Stacks:
Note: When system is not operational intake caps shall be installed in lieu of intake stacks / Q-1
1. Verify impact cup for the Collector intake is clean and in place.
Note: This may require an aloft chit. / Q-1
2. Verify Intake stack caps are clean, dry and can be easily removed (not frozen in place). Note: This may require an aloft chit. / Q-1
3. Verify intake stacks are clean, dry and can be easily removed (not frozen in place). Note: This may require an aloft chit. / Q-1
b. JPBDS Reference Material:
1. Verify BBSU reference card is clean and in place. / A-1
2. Verify dates that the following components were replaced:
3. BAWS Dryer Filter element / A-1
4. Carbon Filter / A-1
5. Particle Filter / A-1

c. LRU and Support Equipment Validation (Serial Numbers)

/ Serial # / S/U
1. Biological Agent Warning Sensor (BAWS) / Annotate PH Level ( )
2. Fluid Transfer System (FTS)

3. Identifier

4. JBPDS Control Assembly (JCA)

5. Collector

6. Basic Biological Suite Unit (BBSU)

7. Verify refrigerator installed/used only for JPBDS support equipment

d. BBSU Setup:

1. Visually inspect BBSU exterior for damage. / 2M-1
2. Visually inspect LCS for damage / smudges. / 2M-1
3. Open BBSU doors and visually inspect all components and connections. / 2M-1
4. Visually inspect internal components for:
Fluid leaks
Air leaks
Tight Connections
5. Inspect FTS shrouds for broken needles.
e. Test Operate JPBDS:
1. Test operate JPBDS in accordance with PMS.
Verify all components are operational.
Verify Time/Location/Weather feed.
Verify BAWS Elastic PHD ____(should be less than 1200) / 2M-1
2. Verify battery power level.
3. Test operate local BBSU alarm. / 2M-1
4. Test operate ship’s chemical alarm. / 2M-1
5. Verify communication with External Control Substations (CIC and DCC). / 2M-1
6. Verify dry collection filter adapter is operational
f. Visually Inspect External Control Substation (ECS). Number of ECS’s is dependent on JBPDS installation date. Initial installations required 2, and installations after October 2008 have only 1 ECS located in DCC/CCS.
1. Inspect for damage and operability.