Banner Project - Finance Module

Event/Activity Calendar

( as of 06/30/05 )

Week of Event/Activity Description Other Banner Project Activities

05/10/05 Copy TEST to CONV (Fri., 05/13/05) HR Workshop #5 (Payroll)

05/16/05 Grant User Access to CONV (Mon., 05/17/05) Student Workshop #7 (Registration/Fee Assessment)

Mission Critical Reports Identified (Wed., 05/18/05)

Approval of Purchase Orders by State Board of Education (Fri., 05/20/05)

AP Checks ordered (Fri., 05/20/05)

Mechanical Entries Script to Dave Neil (Fri., 05/20/05)

05/23/05 COA Testing Completed (Thurs., 05/23/05)

FRS COA to Banner COA Crosswalk Completed (Mon., 05/23/05)

FRS COA Crosswalk published to project web site (Tues., (05/24/05)

05/30/05 Finance Workshop #12 (TBD – Interface Follow-up?)

06/06/05 Clone TEST to PROD (Mon., 6/6/05) – T Bilskie

Q/A Prod database (Wed., 6/8/05) – L Cackler & Finance Team

Migrate Data from Plus to Banner

Location Codes (Tues., 6/7/05) – Q Tao

Vendors (Sat., 06/11/05) – D Seed

06/13/05 Grants setup and assigned to the funds for project accounts (Mon., 06/13/05) – Finance Team

Re-create bank codes, agencies & fims mgr, if applicable (Mon., 06/13/05) – Finance Team

Fiscal Calendar Set By (Mon., 06/13/05)

Finance Workshop #13 (Larry Cackler onsite Wed., 6/15 thru Fri., 06/17/05)

06/20/05

Testing of Cash Receipts in Busar Office (Wed., 06/20/05) – Finance Team

Testing of AP Checks (Wed., 06/22/05) – A Clark/D Thacker

Reload Avail Balances on TEST (Wed., 06/22/05) – T Bilskie

Migrate Data from Plus to Banner

Crosswalks (Fri., 06/24/05) – D Seed

Beginning Balances (Fri., 06/24/05) – D Seed

Budget (Fri., 06/24/05) – D Seed

06/27/05 MIC Workshop (HR Data Conversion)

Plus to Banner Interfaces ( All Required for Go Live ) – D Seed

Plus HRS to Banner Finance (Thurs., 07/07/05)

Plus SIS to Banner Finance (Wed., 07/13/05)

Plus AD to Banner Finance (Fri., 07/15/05)

Printing to Banner Finance (TBD)

External to Banner Interfaces ( All Required for Go Live ) – D Seed

Telephone (07/29/05)

Postage (Fri., 07/08/05)

Staples (Mon., 07/15/05)

Commercial Printing (TBD)

*** All Changes to PROD must be approved by Finance Leadership *** (Wed., 06/29/05)

Contingency Plan Complete (Wed., 06/29/05)

Nightly Processing (Fri., 07/01/05) – T Bilskie

COA Update Process Documented (Fri., 07/01/05) – D Seed/C Wampler

Finance Workshop #14 (Larry Cackler onsite Tues., 06/28/05 thru Fri., 07/01/05)

All Finance Users setup in PROD (Fri., 07/01) – J McCarty/C Wampler

Set Fiscal /NSF parameters (TBD) – Finance Team

Rebuild Budget Available Balances (TBD) – T Bilskie

Scrub Finance Transactions from PROD (TBD) – T Bilskie

Load Budget into PROD (TBD) – D Seed

Validation of PROD (TBD) – Finance Team

07/04/05 All reports necessary for Go-Live completed (Mon., 07/04/05) – D Thacker

*** Freeze of PROD, no more changes ***

Clone PROD to PPRD (Tues., 07/05)

Finance Go-Live (Tues., 07/05)

Clone PROD to PPRD (Tues., 07/05/05) – T Bilskie

Bank Reconciliation Testing (Wed., 07/06/05) – D Seed

Mechanical Entries tested in PROD (Thurs., 07/07/05) – T Bilskie

Ad-hoc Reporting Tool Training (Fri., 7/8/05) – T Bilskie

Aug/Sept Fund Balances, Grant Revenue/Expenses Go Live

10/03/05 Finance Workshop #13 (HR/FI Joint Position Control)

Oct/Nov Fixed Assets migrated

Dec 1099’s

05/01/06 Finance Workshop #14 (Year End Processing)

System Education identified to be addressed post 7/1/05:

Budget Development and Position Control

Year End

Cost Accounting & Stores Inventory

Endowment