BANGALORE ELECTRICITY SUPPLY COMPANY LIMITED

(Wholly Owned Government of Karnataka Undertaking)
Email ID:
Ph. No.
No. CEE/BRAZ/SEE(O)/AEE-3 /12-13/
Encl: 1 / Office of the
Chief Engineer Electy.,
IT Park, 5th floor,
Rajajinagar industrial Area.
Bangalore – 44,
Date:

To,

The General Manager (El),

Customer relations,

Corporate office, BESCOM

K.R Circle, Bangalore.

Sir,

Sub: - Requisition for Line clear at various substations coming under BRAZ Circle for the month of Feb-2013.

Ref:-1) No: SEE/Tr(M)/BRAZ/EE(O)/AEE-01/F-L2/ 2012-13/6182-87 dt:24.1.13 (with Revised dates requested email dt:15.02.2013)

I am herewith enclosing the request letter of Superintending Engineer; Trans (Maint), BRAZ, KPTCL vide reference for availing line clear for the following stations for quarterly maintenance.

Sl
no / NAME OF THE STATION / Date of last maintenance carried out / Men available / Duration / Preferable Date / Areas affected / CONSUMERS AFFECTED IN NO.S / No. of O & M Sub-Division
1 / 220/66/11KV R/S Dabespet / 08.11.2012 / 12Nos. / 9.00 Hrs to 16.00 Hrs / 27.02.2013 / 66/11 KV S/S Nelmangala/ T-Begur/ Thyamagondlu, Hirehalli, Baddihalli, Hoonudike, Dabespet Local / - / Nelamangala
2 / 66/11 KV S/S Nelmangala / 08.11.2012 / 11 Nos / 9.00 Hrs to 16.00 Hrs / 27.02.2013 / F1- Thyamagondlu, F4- Industrial Area, F5- Madavara, F10- Himalaya Drug, F12- VV Pura, F2-KBDL, F7- C-Factory, F8- Nelamangala Town, F9- Sondekoppa, F-11 Organic, F13-KV Aux feeder, F14- Keser Marble, F15- Pepsi, F16- Yentaganahalli, F17- Ramco Biotech, F18- Vijaya Steel, F19- T-Begur, F20- Gollahalli, F22- Denso / - / Nelamangala
3 / 66/11 kv S/S T-Begur / 29.12.2012 / 10 / 9.00 Hrs to 16.00 Hrs / 21.02.2012 / F2- Indus Fila, F3- Pepsi, F10- Gedadlahalli, F9- Bardi, F7- Hasarvalli, F6- Kirloskar, F8- Filament / - / Nelamangala
4 / 66/11 kv S/S, Thyamagondlu / 29.12.2012 / 10 / 9.00 Hrs to 16.00 Hrs / 21.02.2012 / F1- BigBag, F2- TRMN, F3- Satarac, F4-Kallagatta, F9- Rama Hi-Power, F5- GundenaHalli, F6- KSDL, F7- Beeragondanahalli, F8- TotanaHalli / - / Nelamangala
5 / 66/11 kv S/S Magadi / 20.11.2012 / 8 / 9.00 Hrs to 16.00 Hrs / 26.02.2012 / 1- KEB colony, F2-magadi town, F3- Kaleya, F4-G.M.Hally, F10- Manchanebele water supply, F8- Thaggikuppe, F7- G.M.Hally express, F9- savanadurga, F11- Managal, F12- Kalyagate / - / Magadi
6 / 66/11 kv S/S T.G.Halli / 20.11.2012 / 9 / 9.00 Hrs to 16.00 Hrs / 26.02.2012 / F1- Gangapanahalli, F2- Hulevenahalli, F3- Motaganahalli, F4- varadenahalli / - / Tavarekere and Magadi
7 / 66/11 kv S/S Gudemaranahalli / 20.11.2012 / 6 / 9.00 Hrs to 16.00 Hrs / 26.02.2012 / F1- Solur, F5- Chilling Center, F7- Gudemaranahalli, F8- Bittasandra / - / Kudur
8 / 66/11 kv S/S Tavarekere / 23.11.2012 / 9 / 9.00 Hrs to 16.00 Hrs / 20.02.2012 / F5- Metepalya, F6- Stone Crusher, F7- Janapriya, F8- Kadabegere, F9- ISRO / - / Tavarekere
9 / 66/11 kv S/S V.G.Doddi / Station Commissioned on 24.08.2012 and load taken on 01.09.2012 / 8 / 9.00 Hrs to 16.00 Hrs / 22.02.2012 / F3- V.G.Doddi, F4- Gavinagamangala / - / Magadi
10 / 220/66/11n kv R/S Ekarajapura / 27.11.2012 / 10 / 9.00 Hrs to 04.00 Hrs / 22.02.2012 / Areas pertaining to the following 66/11 KV S/S. 1) Pillaguppa. 2)Nandagudi. 3) Sulebele 4) Volvo 5) HBR 6) Vidyanagar 7) Manyatha 8) EHT GrindwellNortan / - / Hosakote , Nandagudi , Additional East (E5) , Devanahally

Hence, line clear concurrence may be issued for above stations on above mentioned dates, so that necessary paper notification will be issued by the concerned Executive Engineers for power supply affected areas.

Yours faithfully,

Chief Engineer Electy.,

BRAZ, BESCOM.

Copy to:

1)The CGM operations, Corporate office Bangalore for information and needful.

2)The Superintending Engineer Ele., O&M Circle, BRC, BESCOM.

3)The Executive Engineer Ele., Yelahanka,Nelmangala division, BESCOM.

4)AEE-3/ MF.