Arizona Public Service Company

Arizona Public Service Company

Arizona Public Service Company

PROPOSAL DEVELOPMENT PLAN

Arizona Public Service Company

Proposal for Photovoltaic (PV) Generation Resources

PROPOSAL DEVELOPMENT PLAN

February 15, 2010

Revision Tracking

Date / Rev #

SECTION / TITLE PAGE

1.0General Information______2

2.0Proposal Team______3

3.0Proposal Schedule______3

4.0Proposal Assignments______4

1.0GENERAL INFORMATION

Proposal Name: Arizona Public Service Company (APS) for PV Generation Resources

Request for Proposal No.: N/A

Charge Number: N/A

1.1Delivery Information

Due: Wednesday, April 7, 2010, (NO TIME SPECIFIED ASSUMING COB)

Submit To:

1.2Submittal Requirements

  • Intent to Bid Document – This is a non-binding document and must be posted to Power Advocate by March 24, 2010.
  • Signed Confidentiality Agreement (CA) – Must be posted to Power Advocate by March 31, 2010.
  • A non-refundable RFP submission fee of $5,000 per Respondent is required in order to qualify the Proposal(s) for consideration. Respondents may make up to 4 proposals for $5,000. Additional proposals will require an additional $5,000 fee. The fee must be received by the response date shown in Section 1.4 (April 7, 2010) and must be wired using the following information:

Company: Arizona Public Service Company

Bank: Wells Argo

ABA/Routing No:121000248

  • Proposal and supporting documents submitted via Power Advocate -

1.3 Pre-Proposal Meeting

  • BIDDER’S CONFERENCE – March 12, 2010

1.4Questions:

This is covered in section 1.5.2 of the RFP:

It is the Respondent’s responsibility to advise APS’s Official Contact of any conflicting requirements, omissions of information, or the need for clarification before Proposals are due. There is no specific date mentioned for questions to be in.

The Official Contact is Gordon Samuel – Address above – No email available. Since this goes through PowerAdvocate I assume his email is linked to the site.

1.5Evaluation Criteria

Evaluation Item
Pricing
Experience and Capabilities of Project team
Proposed System Conceptual Design & Technical Specifications
Financial Capability
Solar Equipment Supply

2.0PROPOSAL TEAM

2.1Team Organization

Prime:Pike Electric

Subcontractors: TBD

2.2Proposal Team Contact Information

Name/Role / Phone / Fax / E-mail / Office Location
Jim Hicks / 704.510.3702 / 704.510.3799 / / Charlotte, NC
Ed Spooner / 704.510.3148 / 704.510.3799 / / Charlotte, NC
Brian Hay / 704.510.3705 / 704.510.3799 / / Charlotte, NC
John Kiser / 704.510.3708 / 704.510.3799 / / Charlotte, NC
Amber Mann / 704.510.3765 / 704.510.3799 / / Charlotte, NC
Glen Allen / 704.510.3712 / 704.510.3799 / / Charlotte, NC
John Rhyne / 704.510.3781 / 704.510.3799 / / Charlotte, NC
Mary Williams / 704.510.3132 / 704.510.3799 / / Charlotte, NC
Jackie Panos / 704.510.3777 / 704.510.3799 / / Charlotte, NC
Joel Olsen / 704.490.9696 / / Cornelius, NC
Rebekah Hren / 336.266.8800 / / Durham, NC

3.0 PROPOSAL SCHEDULE

March 2010
Sunday / Monday / Tuesday / Wednesday / Thursday / Friday / Saturday
7 / 8 / 9 / 10 / 11 / 12
BIDDER’S CONFERENCE / 13
14 / 15 / 16 / 17 / 18 / 19 / 20
21 / 22 / 23 / 24
NOTICE OF INTENT TO BID DUE / 25 / 26 / 27
28 / 29 / 30 / 31
SIGNED CONFIDENTIALITY AGREEMENT DUE
April 2010
Sunday / Monday / Tuesday / Wednesday / Thursday / Friday / Saturday
4 / 5 / 6 / 7
RFP Responses and Submittal Fee Due / 8 / 9 / 10

Page 1 of 9

Arizona Public Service Company

PROPOSAL DEVELOPMENT PLAN

4.0 PROPOSAL ASSIGNMENTS

No.

/

Title

/

Description

/

Lead Assigned to

/

Due Date

/

% Complete

/

Notes

4.1 / Cover Page / Williams /
1/18/10
/ 0% / 4.2 / TAB 1 – OUC Compliance Forms /
  • Declarations & Signatures
/ Williams / 1/18/10 / 0% /
  • Dispute Disclosure
/ Williams / 1/18/10 / 0% /
  • Assumptions and Clarifications
/ Spooner / 1/18/10 / 0% /
Needs input from O2 Energies
  • Notice of Negotiation Procedures
/ Williams / 1/18/10 / 0% /
  • PPA Developer General Information
/ Williams / 1/20/10 / 0% / 4.3 / TAB 2 – Licenses and Certifications /
  • Copy of PPA Provider’s Business License
/ Williams / 1/20/10 / 0% /
  • Copy of PPA Provider’s Insurance Certificate
/ Williams / 1/20/10 / 0%
  • Copy of NABCEP Certification
/ Williams / 1/18/10 / 0%
  • Copy of Pike’s Virginia Electrical Contractors License
/ Williams / 1/18/10 / 0%
  • Copy of Pike ’s Business License
/ Williams / 1/18/10 / 0%
  • Copy of Pike’s Insurance Certificate
/ Williams / 1/18/10 / 0%
4.4 / TAB 3 – Financial Information /
  • Background Information for PPA Firm
/ Williams / 1/20/10 / 0%
  • Proposed Pricing Schedule
/ Olsen / Spooner / 1/20/10 / 0% / Use OUC template
  • PPA firm audited financial statements/annual reports (3 yrs)
/ Spooner / Olsen / 1/20/10 / 0%
  • References of current and/or recent power supply agreements with wholesale customers
/ Olsen / Spooner / 1/21/10 / 0%
  • Background Information for Pike
/ Williams / 1/18/10 / 0%
  • Pike’s audited financial statements/annual reports (3 yrs)
/ Williams / 1/18/10 / 0%
4.5 / TAB 4 – Technical Approach /
  • Completed Technical Proposal
/ Spooner / O2Energies / 1/19/10 / 0%
  • Proposed project schedule
/ Spooner / 1/19/10 / 0% /
  • Proposed conceptual design and site layout
/ Spooner / O2Energies / 1/19/10 / 0% /
Based on Kendrick Substation site
  • One-line electrical schematic
/ Spooner / O2Energies / 1/19/10 / 0% /
  • Proposed photovoltaic equipment, inverter and BOS specs
/ Spooner / O2Energies / 1/19/10 / 0% /
  • Letter of Supply Confirmation from module and inverter suppliers
/ Spooner / 1/20/10 / 0% /
Not required but will enhance our proposal
  • Proposed interconnection design
/ Allen / 1/19/10 / 0% /
  • Proposed siting & permitting approach
/ Jenkins / 1/19/10 / 0% /

Summary of requirements and steps to address

4.6 / TAB 5 – Qualifications of the Team /
  • Org Chart
/ Williams / 1/18/10 / 0% /
  • Resumes of Key Project Personnel
/ Williams / 1/18/10 / 0%
  • List proposed major subcontractors
/ Williams / 1/20/10 / 0%
  • Plan for Local Green Job Creation
/ Spooner / Williams / 1/19/10 / 0%
  • MBE/WBE Statement
/ Phoenix / Williams / 1/18/10 / 0%
4.7 / TAB 6 – System Performance Information /
  • Renewable Energy Project Generation Profile
/ O2Energies / 1/20/10 / 0%
  • PVWATTS Data Simulation Results
/ Spooner / 1/18/10 / 0% / Pike Internal
1 / Financial Summary / Development, review and approval of the internal Pike Financial Summary / Spooner / 1/19/10 / 0% / Ready for review
2 / Contract Review / Review and comments on any exceptions to be applied to this proposal response / Kiser / Mann / 1/19/10 / 0%