E. RESUMES OF KEY PERSONNEL PROPOSED FOR THIS CONTRACT(Complete one Section E for each key person.)
12. NAME
Robert DeLoach /13. ROLE IN THIS CONTRACT
Mechanical Engineer /14. YEARS EXPERIENCE
a. TOTAL
58 /b. WITH CURRENT FIRM
3315. FIRM NAME AND LOCATION (City and State)
Beaufort Engineering Services, Inc., Beaufort, SC
16. EDUCATION (DEGREE AND SPECIALIZATION)
BS Mechanical Engineering, Clemson University, SC 1950 /17. CURRENT PROFESSIONAL REGISTRATION (STATE AND DISCIPLINE)
18. OTHER PROFESSIONAL QUALIFICATIONS (Publications, Organizations, Training, Awards, etc.)DoD Certificate of Appreciation for Distinguished Service; Finalist – Beaufort Chamber of Commerce Lifetime Achievement Award. Commendation for Meritorious Civilian Service Medal. Graduated with a Baccalaureate Robert DeLoach has extensive design experience in the field of engineering as a result of 37 years of service holding various positions within the Public Works Department at Parris Island.
19. RELEVANT PROJECTS
a / (1) TITLE AND LOCATION (City and State)Marine Corps Air Station (MCAS), Pass & ID Main Gate Security Improvements, Beaufort, SC / (2) YEAR COMPLETED
PROFESSIONAL SERVICES
2006 /
CONSTRUCTION (If Applicable)
2007(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE / [X ] Check if project performed with current firm
Role: Mechanical Engineer. Mr. DeLoach Conducted pre-design meetings with the Project Manager and all disciplines to assign specific tasks and schedule coordination meetings with “Interdisciplinary Redicheck Review” at 15%, 30% and 60% production stages. After the completion of plans and specifications; Mr. DeLoach conducted a complete “Redicheck Review” of the project providing a written list of review comments and drawings and specifications that have been marked in color. As a Mechanical Engineer, Mr. DeLoach performed field investigations and the verification of site drawings. He also designed a new HVAC system, utilizing air-to-air heat pumps with passive reheat using a heat pipe. Cost of Work: $1.6M.
b / (1) TITLE AND LOCATION (City and State)
Marine Corps Air Station (MCAS), Repair/Addition Building 584
Beaufort, SC / (2) YEAR COMPLETED
PROFESSIONAL SERVICES
2008 /
CONSTRUCTION (If Applicable)
2008(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE / [X ] Check if project performed with current firm
Role: Mechanical Engineer. Mr. DeLoach designed Replacement of the HVAC package systems with split system water to air heat pumps for multiple zones. The existing earth coupled geothermal loop was reused and expanded with new loops/wells to support the new CID addition, Provided a new web based DDC control system for all HVAC and domestic water heating equipment compatible with base energy management system. Plumbing systems were designed to suit new bathroom layouts with new fixtures. Existing utility service lines for DWV and water were reused to serve the new systems. Cost of Construction: $138K.
c / (1) TITLE AND LOCATION (City and State)
Marine Corp Air Station (MCAS), Repairs to Building 566 Chapel Beaufort, SC / (2) YEAR COMPLETED
PROFESSIONAL SERVICES
2004 /
CONSTRUCTION (If Applicable)
2007(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE / [X ] Check if project performed with current firm
Role: Mechanical Engineer. Mr. DeLoach redesigned existing Water Source Heat Pump HVAC systems for areas being renovated by removing, storing, and protecting for reuse. Geothermal earth coupled piping systems were modified and re-piped. New building systems for the addition included high efficient water to air heat pump, new condenser water pumps, and expanded earth coupled piping. A new web based DDC control system was provided compatible with base energy management system. Mr. DeLoach designed new plumbing systems for new ADA toilets. The existing building was occupied during construction requiring that systems be maintained in service to maximum extent possible, phasing work to minimize interruptions. Cost of Construction: $1M.
d / (1) TITLE AND LOCATION (City and State)
Marine Corps Recruit Depot (MCRD), Repair 4160 Electrical Distribution, Beaufort, SC / (2) YEAR COMPLETED
PROFESSIONAL SERVICES
2008 /
CONSTRUCTION (If Applicable)
2009(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE / [X ] Check if project performed with current firm
Role: Mechanical Engineer. Conducted pre-design meetings with Project Manager and all disciplines to assign specific tasks and schedule coordination meetings with “Interdisciplinary Redicheck Review” at 15%, 30% and 60% production stage. After completion of plans and specifications, QAC conducts a complete “Redicheck Review” of the project providing written list of review comments and drawings and specifications that have been marked in color. Cost of Construction: $2.4M.
e / (1) TITLE AND LOCATION (City and State)
U.S. Naval Hospital Renovations to Branch Dental Clinic Building 674, Beaufort, SC / (2) YEAR COMPLETED
PROFESSIONAL SERVICES
2005 /
CONSTRUCTION (If Applicable)
2007(3) BRIEF DESCRIPTION (Brief scope, size, cost, etc.) AND SPECIFIC ROLE / [X ] Check if project performed with current firm
Role: Mechanical Engineer. Coordinate design of demolition of existing inefficient mixed air multi-zone AHU’s with hot deck and cold deck systems. Mr. DeLoach designed the replacement system, a more efficient cold deck/by-pass deck AHU’s with individual zone hot water duct mounted reheat coils (Texas run-around). He designed a DDC controls system to provide efficient operating sequences for the air conditioning system.
Cost of Construction: $550K
STANDARD FORM 330 (6/2004) PAGE