Republic of Nigeria
National Urban Water Sector Reform Project (Cr. 3924-UNI)
Procurement Plan
(February 2006)
I. General
1. Project information
Country: Federal Republic of Nigeria
Project Name: National Urban Water Sector Reform Project
Borrower: Federal Republic of Nigeria
Implementing Agencies: Federal Ministry of Water Resources
Kaduna State Water Board
Kano State Water Board
Ogun State Water Board
2. Bank’s approval Date of the procurement Plan
Original: June 2004
Revision 1: January 2006
3. Date of General Procurement Notice: June 2004
4. Period covered by this procurement plan: CY 2005 & 2006
II. Goods and Works and non-consulting services.
1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement are as follows:
Goods
Procurement Method / Prior Review Threshold(US$ equivalent) / Comments
1. / ICB (Goods) / ³ 250,000 / All
2. / NCB (Goods) / >30,000 to 250,000 / 1st Contract Only
3. / Shopping / <30,000 / None
Works
Procurement Method / Prior Review Threshold(US$ equivalent) / Comments
1. / ICB / ³ 1, 000,000 / All
2. / NCB / 1,000.000 / 1st Contract Only
3. / Shopping / <100,000 / None
4. / Force Account / <50,000 / None
2. Prequalification.Bidders for most civil works contracts shall be pre-qualified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines.
3. Proposed Procedures for CDD Components: N/A
4. Project Operational/Procurement Manual: The implementing agencies have prepared a draft Project Implementation Manual. This manual, among other topics, describes in detail the procurement procedures to be followed by the implementing agencies.
5. Any Other Special Procurement Arrangements: The project permits retroactive financing for eligible works expenditures made after December 31, 2003.
6. Procurement Packages with Methods and Time Schedule
Notes: ICB=International Competitive Bidding
NCB=National Competitive Bidding
Kano State has no current procurement plan
III. Selection of Consultants
1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants is as follows:
Consultants
Selection Method / Prior Review Threshold(US$ equivalent) / Comments
1 / Firms (QCBS) / >200,000 / All
2 / Single Source (SS)/Firms/ Individual / All / All
3 / Firms (QCBS-CQS-LCS) / 100,000 / None
4 / Individual Consultants (IC) / >50,000 / All
5 / Individual Consultants (IC) / <50,000 / None
6 / Annual Training Plan / All / ALL
2. Short list consisting entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may consist entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.
3. Other Special Selection Arrangements: The project permits retroactive financing for eligible expenditures made after December 31, 2003.
4. Consultancy Assignments with Selection Methods and Time Schedule
Notes: SS = Single Source Selection
QCBS=Quality & Cost Base Selection
CQS=Selection Based on Consultants’ Qualifications
Kano State has no current procurement plan.