SECTION 260500 - COMMON WORK RESULTS FOR ELECTRICAL

PART 1 - GENERAL

1.1  RELATED DOCUMENTS

  1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division01 Specification Sections, apply to this Section.

1.2  SUMMARY

  1. This Section includes the following:
  2. Supporting devices for electrical components.
  3. Electrical demolition.
  4. Cutting and patching for electrical construction.
  5. Touchup painting.
  6. Related Sections includes the following:
  7. Division 3 Section “Cast-In-Place Concrete” for concrete outdoor lighting pole bases and indoor equipment bases.
  8. Division 26 Section “Low-Voltage Electrical Power Conductors and Cables” for wires, cables and wiring methods.
  9. Division 26 Section “Raceways and Boxes for Electrical Systems” for raceways, boxes and installation methods.
  10. Division 26 Section “Identification for Electrical Systems” for nameplates and labels for electrical equipment.

1.3  QUALITY ASSURANCE

The following terms apply: furnish means that the contractor shall purchase the equipment; install means that the contractor shall perform the required labor; provide means furnish and install.

  1. Weekly, the Contractor(s) shall maintain legible field mark-ups (red lines) on the MASTER Project Control Documents reflecting as-built conditions. The red lines will be forwarded to site manager upon completion of the work. A system walkthrough with a field representative will be required upon completion of work.
  2. Field verify all existing conditions, locate and coordinate all new and existing work as required to avoid interferences, maintain equipment clearances and allow for maintenance access.
  3. Contractor is responsible to maintain a clean GMP worksite. All construction debris is to be removed on a daily basis. All walkways and access points are to be kept clear of any obstructions during construction.
  4. Contractor is responsible for coordinating all work through site manager prior to performing any work.
  5. Contractor shall meet all building safety requirements (LO/TO, fire watch, etc… as applicable).
  6. Contractor shall field verify each branch circuit/feeders, and document existing and new conditions.
  7. The Contractor(s) is responsible for coordinating all work with other disciplines through Chrysler Engineer.
  8. All completed work must comply with government safety regulations including OSHA (29 CFR Part 1910) and MIOSHA General Industry Standards.
  9. The Selected Trade Contractor will provide all required materials, equipment, labor, subcontractors, supervision, bulk commodities, permits, insurances, and consumables in accordance with the Contract Documents to fulfill the contract requirements.
  10. The contractor shall carry the work of this project in accordance with all Chrysler standards whether or not they are specifically identified on the drawings/documents.
  11. All activities and work associated with this project will conform and comply with applicable, local, state, and federal regulations, ordinances, codes, standards, laws, and other similar governing documents and bodies.
  12. References: The following reference documents, their commentaries, and the standards referenced therein apply to the design, fabrication and construction of the Work.
  13. National Electrical Code (Current Edition).
  14. OSHA CFR29, Parts 1900 to 1910 and 1926 and applicable MIOSHA standards.
  15. Factory Mutual Loss Prevention Data Handbook.
  16. American National Standards Institute.
  1. Contractor shall provide supervision, labor, materials, equipment, and all other items as necessary to complete the work as defined on this document.
  2. Comply with NFPA70 for components and installation.
  3. Listing and Labeling: Provide products specified in this Section that are listed and labeled.
  4. The Terms "Listed and Labeled": As defined in the National Electrical Code, Article 100.
  5. Listing and Labeling Agency Qualifications: A "Nationally Recognized Testing Laboratory" (NRTL) as defined in OSHA Regulation 1910.7.

1.4  SEQUENCING AND SCHEDULING

  1. Coordinate electrical equipment installation with other building components, and the work of other Contracts.
  2. Coordinate installing required supporting devices and set sleeves in poured-in-place concrete and other structural components as they are constructed.
  3. Sequence, coordinate, and integrate installing electrical materials and equipment for efficient flow of the Work. Coordinate installing large equipment requiring positioning prior to closing in the building.
  4. Coordinate connecting electrical service to components furnished under other Sections.

PART 2 -

2.1  SUPPORTING DEVICES

  1. Channel and angle support systems, hangers, anchors, sleeves, U-bolt beam clamps, brackets, fabricated items, and fasteners are designed to provide secure support from the building structure for electrical lighting fixtures and components.
  2. Material: Steel, except as otherwise indicated, protected from corrosion with zinc coating or with treatment of equivalent corrosion resistance using approved alternative finish or inherent material characteristics.
  3. Metal Items for Use Outdoors or in Damp Locations: Hot-dip galvanized steel, except as otherwise indicated.
  4. Steel channel supports have 9/16-inch diameter holes at a maximum of 8 inches on center, in at least one surface.
  5. Fittings and accessories mate and match with channels and are from the same manufacturer.
  6. Raceway and Cable Supports: Manufactured clevis hangers, riser clamps, straps, threaded C-clamps with retainers, ceiling trapeze hangers, U-bolt beam clamps, wall brackets, and spring steel clamps or "click"- type hangers.
  7. Sheet-Metal Sleeves: 0.0276-inch or heavier galvanized sheet steel, round tube, closed with welded longitudinal joint.
  8. Pipe Sleeves: ASTMA53, TypeE, GradeA, Schedule40, galvanized steel, plain ends.
  9. Expansion Anchors: Carbon-steel wedge or sleeve type.
  10. Toggle Bolts: All-steel springhead type.
  11. Powder-Driven Threaded Studs: Heat-treated steel.

2.2  TOUCHUP PAINT

  1. For Equipment: Provided by equipment manufacturer and selected to match equipment finish.
  2. For Nonequipment Surfaces: Matching type and color of undamaged, existing adjacent finish.
  3. For Galvanized Surfaces: Zinc-rich paint recommended by item manufacturer.

PART 3 - EXECUTION

3.1  EQUIPMENT INSTALLATION REQUIREMENTS

  1. Install components and equipment to provide the maximum possible headroom where mounting heights or other location criteria are not indicated.
  2. Install items level, plumb, and parallel and perpendicular to other building systems and components, except where otherwise indicated.
  3. Install equipment to facilitate service, maintenance, and repair or replacement of components. Connect for ease of disconnecting, with minimum interference with other installations.
  4. Give right of way to raceways and piping systems installed at a required slope.

3.2  ELECTRICAL SUPPORTING METHODS

  1. All Locations: Hot-dip galvanized materials or nonmetallic, U-channel system components.
  2. Conform to manufacturer's recommendations for selecting supports.
  3. Strength of Supports: Adequate to carry all present and future loads, times a safety factor of at least 4; 200-lb-minimum design load.

3.3  INSTALLATION

  1. Install wires in raceway according to manufacturer's written instructions and NECA's "Standard of Installation."
  2. Properly tighten conductor connections and terminations:
  3. Tighten connectors and terminals, including screws and bolts, according to equipment manufacturer's published torque tightening values.
  4. Where manufacturer's requirements are not indicated, tighten connectors and terminals according to tightening requirements specified in UL486A and 486B.
  5. Conductor Splices: Keep to the minimum and comply with the following:
  6. Install splices and taps that possess equivalent or better mechanical strength and insulation ratings than unspliced conductors.
  7. Use splice and tap connectors that are compatible with conductor material.
  8. Wiring at Outlets: Provide at least 6inches of slack conductor at each outlet.
  9. Install devices to securely and permanently fasten and support electrical components.
  10. Raceway Supports: Comply with NFPA70 and the following requirements:
  11. Conform to manufacturer's recommendations for selecting and installing supports.
  12. Install individual and multiple raceway hangers and riser clamps to support raceways. Provide U bolts, clamps, attachments, and other hardware necessary for hanger assembly and for securing hanger rods and conduits.
  13. Support parallel runs of horizontal raceways together on trapeze- or bracket-type hangers.
  14. Support individual horizontal raceways with separate, malleable iron pipe hangers or clamps.
  15. Hanger Rods: 1/4-inch diameter or larger threaded steel, except as otherwise indicated.
  16. In vertical runs, arrange support so the load produced by the weight of the raceway and the enclosed conductors is carried entirely by the conduit supports, with no weight load on raceway terminals.
  17. Miscellaneous Supports: Install metal channel supports for lighting fixtures, for rack-mounted cabinets, panelboards, disconnects, control enclosures, pull boxes, junction boxes, transformers, and other electrical devices and components except where components are mounted directly to structural features of adequate strength.
  18. In open overhead spaces, cast boxes threaded to raceways need not be separately supported, except where used for fixture support; support sheet-metal boxes directly from the building structure or by bar hangers. Where bar hangers are used, attach the bar to raceways on opposite sides of the box and support the raceway with an approved fastener not more than 24 inches from the box.
  19. Fastening: Unless otherwise indicated, securely fasten electrical items and their supporting hardware to the building structure. Perform fastening according to the following:
  20. Fasten by means of wood screws or screw-type nails on wood; toggle bolts on hollow masonry units; concrete inserts or expansion bolts on concrete or solid masonry; and by machine screws, welded threaded studs, or spring-tension clamps on steel.
  21. Threaded studs driven by a powder charge and provided with lock washers and nuts may be used instead of expansion bolts, machine screws, or wood screws.
  22. Welding to steel structure may be used only for threaded studs, not for conduits, pipe straps, or any other items.
  23. In partitions of light steel construction use sheet-metal screws.
  24. Drill holes in concrete beams so holes more than 1-1/2 inches deep do not cut main reinforcing bars.
  25. Drill holes in concrete so holes more than 3/4 inch deep do not cut main reinforcing bars.
  26. Fill and seal holes drilled in concrete and not used.
  27. Select fasteners so the load applied to any fastener does not exceed 25 percent of the proof-test load.

3.4  DEMOLITION

  1. Where electrical work to remain is damaged or disturbed in the course of the Work, remove damaged portions and install new products of equal capacity, quality, and functionality.
  2. Accessible Work Indicated to Be Demolished: Remove exposed electrical installation in its entirety.
  3. Abandoned Work: Cut and remove buried raceway and wiring indicated to be abandoned in place, 2 inches below the surface of adjacent construction. Cap and patch surface to match existing finish.
  4. Removal: Remove demolished material from the Project site.
  5. Temporary Disconnection: Remove, store, clean, reinstall, reconnect, and make operational components indicated for relocation.

3.5  CUTTING AND PATCHING

  1. Cut, channel, chase, and drill floors, walls, partitions, ceilings, and other surfaces necessary for electrical installations. Perform cutting by skilled mechanics of the trades involved.
  2. Repair disturbed surfaces to match adjacent undisturbed surfaces.

3.6  TOUCHUP PAINTING

  1. Thoroughly clean damaged areas and provide primer, intermediate, and finish coats to suit the degree of damage at each location.
  2. Follow paint manufacturer's written instructions for surface preparation and for timing and application of successive coats.

END OF SECTION