Board Report

NPRR Number / 771 / NPRR Title / Clarifications to New ESI ID Creation Process
Date of Decision / October 11, 2016
Action / Approved
Timeline / Normal
Effective Date / September 1, 2016
Priority and Rank Assigned / Not applicable
Nodal Protocol Sections Requiring Revision / 15.4.1.4, New Electric Service Identifier Creation
Related Documents Requiring Revision/ Related Revision Requests / None
Revision Description / This Nodal Protocol Revision Request (NPRR) clarifies that the Transmission and/or Distribution Service Providers (TDSPs) must ensure that an Electric Service Identifier (ESI ID) has been created in the ERCOT systems prior to initiating electric service at a Premise. As a result, related transactional, billing and out-of-sync issues may be avoided.
Reason for Revision / Addresses current operational issues.
Meets Strategic goals (tied to the ERCOT Strategic Plan or directed by the ERCOT Board).
Market efficiencies or enhancements
Administrative
Regulatory requirements
Other: (explain)
(please select all that apply)
Business Case / The implementation of this NPRR should eliminate out-of-sync conditions between ERCOT and the TDSP, and resolves a Competitive Retailer’s (CR’s) inability to bill their retail Customer and any related Settlement issues created by the out-of-sync condition.
Credit Work Group Review / ERCOT Credit Staff and the Credit Work Group (Credit WG) have reviewed NPRR771 and do not believe that it requires changes to credit monitoring activity or the calculation of liability.
PRS Decision / On 6/16/16, PRS unanimously voted to recommend approval of NPRR771 as submitted. All Market Segments were present for the vote.
On 7/14/16, PRS unanimously voted to endorse and forward to TAC the 6/16/16 PRS Report and the Impact Analysis for NPRR771. All Market Segments were present for the vote.
Summary of PRS Discussion / On 6/16/16, there was no discussion.
On 7/14/16, there was no discussion.
TAC Decision / On 7/28/16, TAC unanimously voted to recommend approval of NPRR771 as recommended by PRS in the 7/14/16 PRS Report. All Market Segments were present for the vote.
Summary of TAC Discussion / On 7/28/16, there was no discussion.
ERCOT Opinion / ERCOT supports approval of NPRR771 because it will reduce transactional, billing, and out-of-sync issues.
Board Decision / On 8/9/16, the ERCOT Board took no action on NPRR771.
On 10/11/16, the ERCOT Board approved NPRR771 as recommended by TAC in the 7/28/16 TAC Report with an ERCOT Board action effective date of 8/9/16.
Sponsor
Name / Diana Rehfeldt on behalf of Texas SET Working Group
E-mail Address /
Company / TNMP
Phone Number / 800-738-5579 Ext. 5204
Cell Number / 832-221-9905
Market Segment / Investor Owner Utility (IOU)
Market Rules Staff Contact
Name / Lindsay Butterfield
E-Mail Address /
Phone Number / 512-248-6521
Comments Received
Comment Author / Comment Summary
RMS 060716 / Endorsed NPRR771 as submitted.
Market Rules Notes

None

Proposed Protocol Language Revision

15.4.1.4New Electric Service Identifier Creation

(1)Since it is anticipated that the ESI ID will be based on the existing TDSP account or Premise numbers (with a prefix identifying the TDSP), the TDSP will assign and submit to the registration database ESI IDs for new Premises as service is extended to them. TDSPs that opt in after the market startup will be responsible for the creation of ESI IDs for all existing Service Delivery Points in their service territory.

(2)The TDSP will send ESI ID information using the 814_20, ESI ID Maintenance Request. ERCOT will verify that this transaction meets Texas Standard Electronic Transaction (TX SET) specifications. ERCOT will respond to the TDSP within one Retail Business Hour, with acceptance or rejection of these transactions using the 814_21, ESI ID Maintenance Response. At least the following data elements are required to be sent in the 814_20 transaction:

(a)ESI ID;

(b)Service Address; city, state, zip;

(c)Load Profile Type;

(d)Meter reading cycle or meter cycle by day of month;

(e)Station ID;

(f)Distribution Loss Factor (DLF) code; and

(g)Premise type.

(3)The TDSP must receive an accepted 814_21 from ERCOT prior to initiating electric service pursuant to Section 15.1.4, Beginning Service (New Construction Completed and Move Ins).